Fish River dosing plant

Potassium permanganate

About

Reminder note for raw (untreated) water customers only:

Water supplied by the Fish River pipeline is not intended for drinking, cooking, washing clothes etc. This water is still safe for stock and flushing toilets. If you have any concerns, WaterNSW recommends that you contact the Nepean Blue Mountains Local Health Department on (02) 4734 2000 or by email for any further advice.

The recently constructed Potassium Permanganate Dosing Plant at Oberon Pumping Station will reduce manganese levels and discoloured drinking water caused by seasonal changes in raw water from Oberon Dam.

Potassium permanganate is commonly used in water treatment plant processes and will be dosed into the water supply in accordance with current guidelines.

The Duckmaloi Water Filtration Plant already removes some manganese and adding potassium permanganate to the raw water will improve the manganese removal during the water treatment process.

In conjunction with the Potassium Permanganate dosing, WaterNSW will also trial Aluminium Chlorohydrate (ACH) - (another commonly used chemical in water treatment) to check if this further improves drinking water quality supplied to treated water customers. This again will be dosed in line with current Australian Drinking Water guidelines.

The dosing trial is expected to start in Spring 2024 and the plant will mainly operate during summer and autumn when the manganese levels are higher.

The completed Fish River dosing plant sits within a fenced area with a hill in the background.
Potassium permanganate dosing plant next to the Oberon Pumping Station.
Potassium permanganate dosing system including dosing pumps
Potassium permanganate dosing system including dosing pumps

Objectives

WaterNSW is committed to providing high quality drinking water to our filtered water customers. This dosing system will provide us with the capacity to respond immediately to seasonal changes which cause elevated manganese concentrations in water from Oberon Dam.

Schedule

Spring 2024
Expected commencement of trial dosing of both potassium permanganate and ACH.

Consultation

WaterNSW is committed to engaging with the local community. Fish River Water Supply Scheme customers, stakeholders and government agencies will be engaged throughout the process.

WaterNSW will keep the community and stakeholders informed through website updates and campaigns targeted to Fish River Water Supply Scheme customers. If you are a Fish River Water Supply Scheme customer and would like to be kept informed about this project, please send your contact details to our team at: comms.waternsw.com.au/confirmdetails

Contact

For more information about the Potassium Permanganate Dosing Plant, please contact the Customer Service Centre on 1300 662 077 or email Customer.Helpdesk@waternsw.com.au .

Project Manager: Janaka Weeraratne

Go to top